Explore Petaluma’s streets

A companion to Follow the Clucking Money Workshop #3: Petaluma’s Forever Bills.

What is PCI?

The Pavement Condition Index scores a road’s surface from 0 to 100 based on cracks, patches, ruts and other damage. 100 means no defects (2023 report, p. 143). The city surveys every street about every two years, using StreetSaver, the Metropolitan Transportation Commission’s (MTC) system for Bay Area cities.

Citywide average: 55, weighted by pavement area. MTC’s three-year average, the one used in regional rankings, was 50 for Petaluma in 2024 and 67 for the Bay Area.

PhotoConditionPCIShare of city pavement

Categories: 2023 Pavement Management Program Update, p. 6. Shares: our calculation from the city map, by pavement area. Photos: Petaluma Urban Chat; scores are the city’s for each pictured block. Three-year averages: MTC, Pavement Condition of Bay Area Jurisdictions 2024, p. 5, and the MTC PCI page.

PCI Map

Each line is a stretch of street, colored by score. Tap one for details.

Loading map…

PCI by Street Type

TypeLane milesAverage PCI
ArterialE Washington St, McDowell Blvd9363
CollectorMaria Dr, I St7955
ResidentialKeller St, Edith St, Northstar Dr22050

2023 Pavement Management Program Update, p. 2. Example streets and their types: the report’s street inventory (Appendix A). Arterials carry the most traffic across town, collectors feed neighborhood traffic onto them, and residential streets, more than half the city’s pavement, are in the worst shape.

Streets fail slowly, then all at once

Streets wear slowly for about 15 years, then quickly. Below about PCI 60, a street can go from fair to failed in as little as five years (MTC).

Illustrative pavement life cycle A typical street stays above PCI 90 for about 11 years, falls to 60 around year 18, where decline speeds up, and reaches 0 by year 25. Treatments by PCI: light maintenance at 70 to 100, about $12 per square yard; heavy maintenance, about $30, or light rehab, about $105, at 50 to 70; heavy rehab at 25 to 50, about $155; reconstruction below 25, about $320. The citywide average is marked on the curve.

Illustrative, not a forecast for any street. Real timing varies with traffic, climate and design.

Sources and methodology

Shape: a simple illustrative curve, PCI = 100 × (1 − (year ÷ 25)3). It stays above 90 for about 11 years, crosses 60 around year 18 and reaches 0 at year 25. For scale, the 2023 report uses a 20-year design life for new pavement, which it describes as a span of about 17 to 23 years (p. 14), and says well-built pavement can last 20 to 30 years (p. 29). MTC says decline speeds up at PCI 60 and a street can go from fair to failed in as little as five years (Plan Bay Area 2040 Local Streets & Roads Needs Assessment, p. 2).

Treatments and costs: 2023 PMP Update, Figure 3 (p. 29) for which treatment applies at each PCI, and Table 1 (p. 28) for cost per square yard. Between 50 and 70, heavy maintenance is for cracking not caused by traffic loads and light rehab is for load cracking. Costs are the report’s arterial, collector and residential prices averaged by lane miles (93, 79 and 220; see street type), then rounded: $11.70, $31.10, $104.30, $154.10 and $318.10. The report’s condition categories put “failed” at PCI 30 and below (p. 6); its treatment breakpoints put reconstruction at 25 and below.

Citywide marker: PCI 54, the citywide average in the 2023 report, p. 5. The city map’s average at the top of this page also includes some later updates by city staff.

Future scenarios

Pick a goal and a deadline to see the yearly budget it needs, or set a budget and see where the score and the backlog end up.

A rough model, not an engineering forecast. It uses city staff’s unit prices and the city’s stated $200M backlog.

Sources and methodology

The anchors. The consultant’s 2023 PMP Update, pp. 6–8, ran five-year scenarios from a citywide score of 54: $20M a year holds 54; $32.5M a year raises it to 59; $5M a year lets it fall to 47; $0 lets it fall to 44. The backlog grows from about $300M by $142M over the five years at $5M a year, by $74M at $20M, and by $24M at $32.5M. In its “needs” scenario (Appendix B), keeping the network at 80–83 cost $44–53M a year.

Our math. Each year, the score changes by (budget − hold cost) ÷ $12.5M, the consultant’s cost of one extra point a year. The hold cost is $20M at a score of 54 and rises in a straight line to $40M at 83, so higher scores cost more to keep. Below the hold cost, the score falls up to 1.4 points a year at $5M and 2 points at $0, matching the decline scenarios. The backlog changes each year by the consultant’s growth rate for that budget, drawn as straight lines between its three scenarios. Scores stop at 85, just above the consultant’s best case. The grid finds, by trial, the budget that lands on each goal in each timeframe. Within five years the model reproduces all four scenarios within half a point.

Staff prices. The anchors above are in the consultant’s prices. City staff concluded that $59.4M over five years holds the score that the consultant priced at $100M (responses to Council questions, Nov. 4, 2024), so the model counts each dollar as buying 1 ÷ 0.594 of the consultant’s work and scales backlog growth the same way. The starting backlog is the city’s stated $200M. The model starts from the citywide score on the city map. All dollars are 2023/24 dollars, with no inflation.

Limits. The consultant only modeled five years and a few budgets; everything between and beyond is our straight-line extension. Real results depend on which streets get which treatment, and on construction prices.

Cost details

Sealing a street in good shape costs far less than rebuilding a failed one. Two recent Petaluma contracts:

Slurry seal

$2.75/sq yd

About $2,600 for a typical block

FY25/26 citywide maintenance contract, finished January 2026

Rebuild a failed street

~$153/sq yd

About $144,000 for a typical block

Rainier Ave, N McDowell Blvd to Sonoma Mountain Pkwy (0.7 mi, PCI 23–29), $2.88M, awarded February 2026

Construction prices only, without design or inspection. Slurry seal: the contract’s unit price ($30,316 for 11,024 sq yd; completion report, May 4, 2026). Rainier: our math, the $2,884,048 winning bid (award report, Feb. 2, 2026) divided by the project’s 18,813 sq yd on the city map. It also pays for a roundabout and bike lanes. Typical block: the median residential block, about 940 sq yd.

Why seal good streets while bad ones wait?

A good street that slips below PCI 70 needs a much costlier fix. A failed street already needs the costliest fix, so waiting doesn’t push it into a higher category. That’s why the city funds sealing every year alongside rebuilding. StreetSaver “makes preventive maintenance a top priority” for this reason (2023 report, p. 28).

The 2023 report’s estimates

For budgeting, the 2023 report used these all-in costs:

TreatmentTypical workCost per sq ydOne block*
Light maintenanceSlurry seal or micro-surface$11–13$11,000
Heavy maintenanceSeal with dig-out repairs, thin overlay$29–35$27,000
Light rehabilitationOverlay up to 2″, thin mill and fill$101–111$95,000
Heavy rehabilitationThick overlay, full-depth reclamation$144–174$135,000
ReconstructionRebuild the full road section$284–384$267,000

2023 PMP Update, Table 1 (p. 28), residential to arterial. Includes design, ADA ramps, stormwater rules, overhead and a 10% contingency. City staff told the Council these run high for Petaluma (Nov. 4, 2024). *About 940 sq yd at the residential rate.

Rebuilding vs. sealing: about 25× in the 2023 report, 11× statewide ($94.82 vs. $8.37 per sq yd, 2026), and 56× in Petaluma’s recent contracts.

The big picture

The real decision is how much to spend each year. At city staff’s prices:

2023 spending

$5M/yr

54 → 49

Score drops in 5 years; backlog grows from $200M to $275M.

Current plan (2024)

$11.9M/yr

54 → 54

City staff’s estimate to hold the score. The backlog still grows to $244M.

To raise the score

$19.3M/yr

54 → 59

Over 5 years; backlog grows to $214M.

Paving is a values choice. A dollar spent on streets isn’t spent on something else. More maintenance now saves money later. But better streets and the other services Petaluma wants means either cutting other priorities or raising more revenue.

Where the rest of the money goes: budget in brief.

Scenarios: our model from Future scenarios, at city staff’s unit prices. It is anchored on the consultant’s scenarios (2023 PMP Update, pp. 7–8); $19.3M is its $32.5M scenario at staff prices. Current plan: staff report and presentation, City Council meeting of November 4, 2024, item 11.